The Defining Decades: Looking Back on California Cannabis Anniversaries

I’ve hired an architect, now what? Looking ahead to 2028

The Department of Cannabis Regulation’s (DCR) 2027 regular renewal period recently ended on November 2, 2026, though one late renewal window is available through the end of November, subject to late fees. If you haven’t already retained a licensed architect or engineer, don’t wait any longer – review DCR’s 2027 renewal guide blog, watch the 2027 renewal webinar, or read DCR’s reference guide for information on how to complete this milestone. 

For those that’ve completed your 2027 renewal – congratulations! Keep the momentum going and start preparing your site plans ASAP so you can move on to the next step: submitting plans to the Department of Building and Safety (DBS). Outlined below is the step-by-step process for initiating the plan check process with DBS, a necessary step for meeting the milestone requirements for the 2028 renewal period. 

Gather Your Documents

First and foremost, your architect or engineer needs to prepare your plans. Make sure there are no references to cannabis on the plans, as DBS will not be able to approve them. Instead, specify in the “Work Description” section of the building permit application that your project is for a cannabis-related business. Your hired architect or engineer should be able to help you fill it out. 

Along with your prepared building plans, you’ll also need to submit the following documents to DBS: 

  1. INT-4001-FORM (PDF) (DCR Referral for LADBS Plan Check) DCR fills out this form on your behalf. Login into the Accela portal to download the form or contact DCRLicensing@lacity.org if you don’t see it in your account 
  2. LADBS building permits records, plot plans, and Certificates of Occupancy for your premises; available via the LADBS online records system or by submitting a Records Research Request Form to LADBS 
  3. Completed LADBS building permit application (PDF)

How and Where to Submit Your Documents

The building permit application and plan check documents can be submitted in person to LADBS with an appointment or through the ePlanLA portal. Regardless of which method you prefer, start by creating an Angeleno Account. You’ll need this to access ePlanLA, set up in-person appointments, and communicate with relevant agencies through the LADBS Notification Portal, City Planning Application System, and more. 

To submit plans online:

  1. Login to ePlanLA and select Start New Application.
  2. Select the type of building plan check you’re applying for from the below options:
    1. Tenant Improvement
    2. Building > New Building
    3. Building > Addition to Building
    4. Building > Alter/Repair of Building
  3. Fill out the building permit application
  4. Upload the required documents

To submit plans in person: 

  1. Login to BuildLA and select Make an Appointment
  2. For Agency/Department, select Building and Safety (LADBS)
  3. For Service, under Plan Check and Permits, select Building Plan Check - New Plan Submittal
  4. Select the office you want to visit and fill out the requested appointment details
  5. Bring building plans and required documents to the appointment 

When deciding between in person or online plan check, consider which is more important to you: convenience or turnaround time. Using ePlanLA affords the ease of submitting remotely, but it will take a few weeks for your plans to be reviewed, whereas in person plan check means same day feedback. 

For in person appointments, also keep in mind that the size of your project will dictate the type of plan check you undergo. Generally speaking, most non-retail cannabis businesses can expect to undergo Regular Plan Check, while some retail operations with Tenant Improvements and delivery-only businesses may qualify for Counter or Expanded Counter Plan Check. You will be directed to the appropriate counter upon arrival for your appointment, with the main difference being the amount of time it takes to review the plans. 

2028 Renewal Cycle Requirements

Once your plans have been reviewed, you should realistically have everything you need to meet the requirements for the 2028 renewal cycle (in addition to fee payment) that will take place from September 1 to October 31, 2027. Your DBS building permit application number and an in-progress DBS Clearance Summary Worksheet will be provided to you by DBS upon completion of plan review.